Manual Adjustments After AI Scheduling
AI Schedule produces a construction-logical starting point. Manual adjustments let you encode project-specific constraints the AI cannot know: client access restrictions, equipment availability windows, phased handover dates, or contractual milestone pins.
Drawing predecessor links manuallyโ
- Hover over a task bar in the Gantt until the link handle โ a small circle โ appears at the right edge of the bar.
- Drag from the handle to the target successor task and release.
- The default link type is Finish-to-Start.
- To change the link type or add a lag: right-click the link arrow to open the link context menu, or open the Task Detail Panel (right-click the task bar, then Edit task) and modify the predecessor entry there.
- Link types supported: FS (Finish-to-Start), SS (Start-to-Start), FF (Finish-to-Finish), SF (Start-to-Finish).
- To delete a link: right-click the link arrow in the Gantt and choose Delete link.
Linking multiple tasks at onceโ
For linking several tasks in one go, select more than one task bar before right-clicking:
- Ctrl+Click (or Cmd+Click on Mac) task bars to build a multi-selection. Each selected bar gets a numbered badge (โ โกโขโฆ). Ctrl+Click a summary (WBS heading) bar to select its whole leaf subtree in one action.
- With 2 or more tasks selected, right-click any one of them to open the link context menu. Alongside the usual pairwise link-type options, the footer offers:
- Chain All [FS] โ links the selection sequentially in the order you selected them (โ โโกโโขโโฆ), all Finish-to-Start.
- Star From โ โ links every other selected task to the first one you selected (โ โโก, โ โโข, โฆ), all Finish-to-Start.
- Remove All Links Between Selected โ clears any existing links among the selected tasks.
These are manual actions โ the links they create behave exactly like a hand-drawn link. For an AI-assisted alternative that infers construction-logical sequencing for a selection instead of a fixed chain or star pattern, see Refine Selection โ Targeted AI Re-sequencing.
How manual links survive AI re-runsโ
User-set predecessors are stored in the predecessors column in the database, separate from the ai_predecessors column used by AI inference. This separation ensures your manual work is never silently replaced.
When Protect my links is on (the default):
- Items with any user-set predecessor link are skipped by AI inference entirely. The AI does not add, change, or remove links on those items.
- On items the AI does process, user-set links always take merge priority โ the AI can add new AI links but cannot replace yours.
When Protect my links is off:
- The AI may now suggest links for all items, including those with existing user-set links.
- However, user-set links still win at merge time. The only practical difference is that the AI may add additional AI-suggested links to items that already have user-set ones, potentially introducing parallelism the AI judges beneficial.
Start constraints (pinning a task)โ
Drag a task bar left or right in the Gantt to pin its start date. This writes a start_constraint_day value that the CPM engine respects, shifting downstream successors as needed.
Use start constraints for:
- Milestone dates such as regulatory inspections or client occupancy
- Equipment delivery windows where a task cannot begin until a crane or shutter arrives
- Work that cannot start before a specific calendar date regardless of predecessor logic
Task splittingโ
Right-click a task bar in the Gantt and select Split Task Here to model a planned work interruption โ for example, a weekend shutdown during a concrete pour, or a three-day demobilisation window mid-task. The split creates two or more segments that the CPM engine treats as a single logical task with a gap.
Splits are preserved across AI re-runs and are included in all export formats (MS Project XML, Excel, Power BI).
Logging progressโ
Right-click a task bar and choose Log Progress (or open the Task Detail Panel and expand the Progress and Actuals section) to record:
- Actual start and finish dates
- Actual quantity completed
- Percentage complete
The Gantt renders an earned-value progress bar inside the task bar. Progress data drives the S-curve earned-value overlay โ the EV line is plotted against the planned cumulative curve up to the data date you set in the S-curve panel.
Re-scoring after manual changesโ
After manually adjusting links, click Re-score โ visible in the AI Schedule modal footer after any previous run โ to update the S-curve quality badge without triggering a new AI inference run. The re-score computes the four S-curve metrics against the current cash-flow distribution and refreshes the badge immediately. No LLM call is made.
Use Re-score each time you make a significant manual change. If the score drops sharply after linking two tasks, it may indicate an unintended concentration of cost โ worth inspecting the S-curve chart before continuing with further adjustments.